Solicitation Type: ITB
Issued by: Tualatin Valley Water District
Publish Date: Oct 16, 2024 12:00AM
Bids Due Date: Nov 12, 2024 2:00PM (Pacific Daylight Time) add to calendar
Price Range: $1,100,000-$1,300,000
Status: open
Posted: Aug 19, 2024

Description

Sealed Bids for the construction of the Oak St Water Main Replacement, Project No. C12859 (Project) for Tualatin Valley Water District (Owner) will be accepted by Heather Speight, Procurement and Contract Administrator, via Equity Hub’s Bid Locker at https://bidlocker.us/details/4405_Oak_St_Water_Main_Replacement  (Bid Locker), until 2:00 p.m. local time on Tuesday, November 12, 2024 (Bid Closing Time). Bidders must sign up with Bid Locker at https://bidlocker.us/a/tvwd/BidLocker before being allowed to submit a bid.  There is no cost to register.  Any bids received after the Bid Closing Time will not be considered.

Registration with Bid Locker requires a correctly completed Confidentiality Agreement, which is available through the registration process.  Following completion of the requested vendor information and upload of the Confidentiality Agreement, the vendor profile will be sent for a manual approval.  Please allow one business day for your vendor profile to be approved.  If it has not been approved within one business day, or if you have questions about this process, please contact bidsandproposals@tvwd.org. Bidders are advised to ensure that their Bid Locker vendor profile is active and approved a minimum of three business days prior to the Bid Closing Time to prevent any issues with submitting a bid on time.

Bids received by the Bid Closing Time will be publicly opened and read aloud immediately thereafter on a conference call at 971.300.4841, phone conference ID  319 144 281.

Bidders are required to submit a First Tier Subcontractor Disclosure Form (First Tiers), as described by ORS 279C.370.  The First Tiers must be submitted to Bid Locker within two hours of the Bid Closing Time.  The Owner must reject a bid if the Bidder fails to submit the First Tiers to Bid Locker within two hours of the Bid Closing Time.  Original copies of the Bid Security must be submitted to Owner within five business days of the Bid Closing Time as prescribed in Section 00 21 13.

The Project consists of furnishing required labor, equipment, and materials for construction of the following:

1.      Approximately 2,500 linear feet of six-inch and eight-inch restrained ductile iron water main, six hydrants with associated six-inch piping, new valves and associated appurtenances, with five new connections to the existing water system (two hot tap and three in-line connections) with thrust restraints.

2.      Reconnection of 42 residential water services between new water lines and existing meters.

3.      Roadway paving and striping restoration, and other miscellaneous surface restoration.

4.      Abandonment of existing 4-inch and 6-inch water lines, valves, hydrants, and associated appurtenances.

The Engineer’s estimate for this Project is $1,100,000 - $1,300,000.

All work is to be completed according to the schedule provided in the Contract documents. District intends to issue a limited Notice to Proceed date no later than March 10, 2025 for the purposes of ordering materials, with a Notice to Proceed for construction no later than April 28,2025.

Bid Documents may be obtained electronically from Bid Locker or in in either electronic or hard copy format by contacting Plan Center Northwest, LLC, PO Box 2486, Clackamas, OR 97015, Phone: (503) 650-0148, Fax: (503) 650-8273, E-mail: mailto:megan@plancenternw.com, plancenternw.com. If a potential Bidder obtains the Bid documents from Contractor Plan Center, the Bidder is still responsible for registering with Bid Locker to submit their bid.

Addenda will be published to Bid Locker.  Bidders who download bid packages from Bid Locker will automatically be notified via email when addenda are published.  It is the responsibility of the Bidder to obtain all addenda. Bidders are responsible for the cost of obtaining and/or printing the Bid Documents. The Bidder, including subcontractors, will also be responsible for signing a confidentiality agreement prior to obtaining the documents. Return of the documents is not required, and the amount paid for the Bid Documents is nonrefundable.

Bidders are strongly encouraged to attend the optional pre-bid conference for this Project on Thursday, October 24, 2024 at 10:00 a.m. via Microsoft Teams. To receive a calendar invitation, email bidsandproposals@tvwd.org by 3:00 p.m. on Wednesday, October 23, 2024.

Contractors must be qualified in accordance with the applicable parts of ORS 279 to enter into a contract with the Owner for public work in Oregon.  Bidders are required to complete and submit with their bid Section 00 45 13, “Statement of Bidder’s Qualifications”.  The Owner will investigate and determine if the qualifications of the apparent low Bidder meet the minimum requirements as part of its evaluation of the lowest responsive and responsible bid.

No bid will be received or considered by the Owner unless the Bid Form contains, or is accompanied by, a statement by the Bidder as a part of the bid that the provisions required by ORS 279C.800 through 279C.870 pertaining to prevailing wages are included in this Contract.  Contractor licensing under ORS 468A.720 for asbestos abatement is not a requirement of this Project. Each bid must contain a statement as to whether the bidder is a resident bidder as defined in ORS 279A.120.  Each bid must contain a statement as to whether the bidder is registered with the Oregon Construction Contractors Board in accordance with the provisions of ORS 279C.365.

Bids must be submitted on the prescribed forms and must be accompanied by a certified check or bid bond executed in favor of Tualatin Valley Water District in an amount not less than ten (10) percent of the amount bid as described in Paragraph 11.1 of Section 00 21 13 Instructions to Bidders.  The successful Bidder will be required to furnish the necessary additional bond(s) for the faithful performance of the Contract as prescribed in the Contract Documents.

The Owner reserves the right to reject all bids not in compliance with all prescribed public contracting procedures and requirements, including bidder responsibility under ORS 279C.375(3)(b), and may reject for good cause all bids upon the Owner’s finding that it is in the Owner’s or the public’s best interest to do so. The Owner reserves the right to waive informalities and to award a Contract to the qualified lowest responsive and responsible Bidder.

For more information regarding this Project contact Marisa Cummins, Project Manager with Tualatin Valley Water District at marisa.cummins@tvwd.org.

Published October 16, 2024 and October 18, 2024.



Line Items

This solicitation has the following line items for which you can submit a bid. Please review the bidding instructions in the bid documents for information on these line items:

Item No Item Unit of Measure Quantity Cost Required?
1 Mobilization Lump Sum 1.00 Cost Requested Required
2 Health and Safety Lump Sum 1.00 Cost Requested Required
3 Temporary Traffic Control Lump Sum 1.00 Cost Requested Required
4 Erosion Control Lump Sum 1.00 Cost Requested Required
5 Construction Survey Lump Sum 1.00 Cost Requested Required
6 6-Inch Ductile Iron Pipe Ft 80.00 Cost Requested Required
7 8-Inch Ductile Iron Pipe Ft 2420.00 Cost Requested Required
8 6-Inch Small Ductile Iron Fitting Ea 4.00 Cost Requested Required
9 8-Inch Small Ductile Iron Fitting Ea 12.00 Cost Requested Required
10 8-Inch Large Ductile Iron Fitting Ea 3.00 Cost Requested Required
11 8-Inch Gate Valve Ea 13.00 Cost Requested Required
12 Fire Hydrant Assembly Including Tee and 6-Inch Gate Valve Ea 6.00 Cost Requested Required
13 Water Service Reconnection Ea 42.00 Cost Requested Required
14 6x6 Hot Tap Connection Ea 1.00 Cost Requested Required
15 16x8 Hot Tap Connection Ea 1.00 Cost Requested Required
16 Concrete Straddle Block for Ductile Iron Pipe Ea 2.00 Cost Requested Required
17 Concrete Straddle Block for Cast Iron Pipe Ea 1.00 Cost Requested Required
18 CLSM Backfill Lump Sum 1.00 Cost Requested Required
19 2-Inch Blow Off Assembly Ea 1.00 Cost Requested Required
20 2-Inch Combination Air Release Valve Assembly Ea 2.00 Cost Requested Required
21 Remove Existing Valve Can Ea 10.00 Cost Requested Required
22 Remove Existing Hydrant Ea 4.00 Cost Requested Required
23 Pipeline Cleaning, Testing, and Disinfection Lump Sum 1.00 Cost Requested Required
24 Connection to Existing Water System Ea 3.00 Cost Requested Required
25 Abandon Existing Water System Lump Sum 1.00 Cost Requested Required
26 Remove and Replace Concrete Sidewalk Sq Yds 7.00 Cost Requested Required
27 Permanent Asphalt Concrete Trench Restoration Ton 601.00 Cost Requested Required
28 Striping Restoration Lump Sum 1.00 Cost Requested Required
29 Miscellaneous Surface Restoration Lump Sum 1.00 Cost Requested Required

Download Line Items as .CSV

Attachments

This project has the following solicitation documents.

Bid Document File Size Notes
145,374
6,423,206
20,851,392

You will need to:

  • Unchecked Be logged into Bid Locker
  • Unchecked Be registered with Tualatin Valley Water District

Pre-Bid Conference

Bidders are strongly encouraged to attend the optional pre-bid conference for this Project on Thursday, October 24, 2024 at 10:00 a.m. via Microsoft Teams. To receive a calendar invitation, email bidsandproposals@tvwd.org by 3:00 p.m. on Wednesday, October 23, 2024.

Pre-Bid Conference Date
Oct 24, 2024 10:00AM (Pacific Daylight Time) add to calendar

Vendor Questions and Answers

Submitted Questions About This Bid

There are no questions that have been answered and posted by Tualatin Valley Water District.

For Questions or Additional Information, Contact:

Name: Heather Speight
Email: bidsandproposals@tvwd.org

Interested Parties and Planholders

Interested Parties

These are the vendors who have expressed interest in this solicitation:

Business When
Compass Land Surveyors Oct 18, 2024
(sub)
DJC Oregon Project Center Oct 16, 2024
(plan center)
K&E Excavating, Inc. Oct 16, 2024
(prime)
Lyda Excavating, Inc. Oct 16, 2024
Moore Excavation Inc. Oct 18, 2024
(prime)
Plan Center Northwest Oct 16, 2024
(plan center)
Salem Contractors Exchange Oct 16, 2024
(plan center)
Seattle Daily Journal of Commerce Oct 16, 2024
(plan center)
SLE Inc. Oct 22, 2024
(prime)
Trench Line Excavation, Inc. Oct 16, 2024
(prime)

Planholders

These are the vendors who have downloaded the solicitation documents:

Business When
Compass Land Surveyors Oct 18, 2024
K&E Excavating, Inc. Oct 16, 2024
Kerr Contractors Oregon, LLC Oct 16, 2024
(prime)
Lyda Excavating, Inc. Oct 16, 2024
(prime)
Moore Excavation Inc. Oct 18, 2024
(prime)
Pihl, Inc. Oct 17, 2024
(prime)
SLE Inc. Oct 22, 2024
Trench Line Excavation, Inc. Oct 16, 2024
(prime)
Turney Excavating Inc. Oct 16, 2024
(prime)

Commodity Codes

Commodity Codes (NIGP):

913-60
Construction, Water System, Plants, Main And Service Line
913-78
Maintenance And Repair, Pipeline, Including Removal And Relocation
913-90
Maintenance And Repair, Viaduct

About Tualatin Valley Water District

Contracting with TVWD

TVWD is a special district, established to provide drinking water, and is governed by an elected Board of Commissioners.  Because some of the information in our solicitations is confidential and protected under US law, all vendors are required to complete a Confidentiality Agreement prior to their TVWD Bid Locker profile being approved. This approval is a manual process.  Please allow one business day for approval and follow any emailed instructions received. TVWD is not responsible for vendors who cannot download and/or submit solicitation responses due to vendor profiles that are not approved.

Public agencies with questions about a solicitation should call 503.848.3055 or email bidsandproposals@tvwd.org for information.  Vendors who reach out directly will be redirected to the instructions in the specific solicitation or other emailed instructions.