Project #: 3982-23
Issued by: City of Beaverton, OR
Publish Date: Feb 1, 2023 8:00PM
Bids Due Date: Mar 7, 2023 2:00PM (Pacific Daylight Time) add to calendar
Status: noaward
Award Notes: Hello All, Please see the cancellation notice for this ITB and the reasoning included therein. The City of Beaverton appreciates your time and will be re-bidding this project shortly. Thank you.
Posted: Feb 1, 2023

Description

 The City of Beaverton is accepting will only accept electronic bids for the project, CONSTRUCTION OF ADA CURB RAMP RETROFIT UPGRADE PROJECT., Project No. 3982-23. It is the City’s intent to enter into one-year contract with the option to renew for additional one-year term with the total term not to exceed two years. Year one project consists of removal of 2,175 feet of curb, removal of 1,091.3 square yards of walk and driveways, 505 square yards of 4” asphalt pavement repairs approximately requiring 96 tons of asphalt, placing 2,175 feet of curb and gutter, placing 9,826 square feet of monolithic curb and sidewalk and approximately 110 tons of aggregate. The project cost is approximately between $900,000.00 and $1,000,000.00. Year two project consists of 1677 feet of curb, removal of 1,185 square yards of walk and driveways, 439 square yards of 4” asphalt pavement repairs approximately requiring 84 tons of asphalt, placing 1,183 feet of curb and gutter, placing 12,412 square feet of monolithic curb and sidewalk and approximately 132 tons of aggregate. The project cost is approximately between $900,000.00 and $1,000,000.00. Both projects are on-site design-build with no plans for ADA curb ramps design.



Line Items

This solicitation has the following line items for which you can submit a bid. Please review the bidding instructions in the bid documents for information on these line items:

Item No Item Unit of Measure Quantity Required?
TEMPORARY FEATURES AND APPURTENANCES
1 Mobilization LS 1.00 Required
2 Temp. Work Zone Traffic Control, Complete LS 1.00 Required
3 Erosion Control LS 1.00 Required
4 Inlet Protection EA 35.00 Required
5 Pollution Control Plan LS 1.00 Required
ROADWORK
6 Removal of Curb FT 2175.00 Required
7 Removal of Walks & Driveways SY 1091.30 Required
8 Asphalt Pavement Saw Cutting FT 2489.00 Required
9 Clearing and Grubbing LS 1.00 Required
DRAINAGE AND SEWERS
10 3 Inch, PVC Pipe, (Weep Holes) FT 46.00 Required
11 4 Inch Asphalt Concrete Pavement Repairs SY 505.30 Required
12 Concrete Curb, Curb and Gutter FT 2175.00 Required
13 Monolithic Curb and Sidewalk SF 9825.50 Required
14 Truncated Dome on New Surface SF 1130.00 Required
PERMANENT TRAFFIC CONTROL AND ILLUMINATIN SYSTEM
15 Remove and Reinstall Existing Signs LS 1.00 Required
RIGHT OF WAY DEVELOPMENT AND CONTROL
16 Single Mailbox Support EA 6.00 Required
17 Reinstall USPS Cluster Mailbox EA 2.00 Required
WATER SUPPY SYSTEM
18 Relocate Irrigation System LS 1.00 Required
 
 
TEMPORARY FEATURES AND APPURTENANCES
1 Mobilization LS 1.00 Required
2 Temp. Work Zone Traffic Control, Complete LS 1.00 Required
3 Erosion Control LS 1.00 Required
4 Inlet Protection EA 18.00 Required
5 Pollution Control Plan LS 1.00 Required
ROADWORK
6 Removal of Curb FT 1677.00 Required
7 Removal of Walks and Driveways SY 1185.40 Required
8 Asphalt Pavement Saw Cutting FT 2164.50 Required
9 Clearing and Grubbing LS 1.00 Required
DRAINAGE AND SEWERS
10 3 Inch, PVC Pipe, (Weep Holes) FT 8.00 Required
WEARING SURFACES
11 4 Inch Asphalt Concrete Pavement Repairs SY 439.20 Required
12 Concrete Curb, Curb FT 82.50 Required
13 Concrete Curb, Curb and Gutter FT 1183.20 Required
14 Monolithic Curb and Sidewalk SF 12412.20 Required
15 Truncated Dome on New Surface SF 736.00 Required
PERMANENT TRAFFIC CONTROL AND ILLUMINATIN SYSTEM
16 Remove and Reinstall Existing Signs LS 1.00 Required
RIGHT OF WAY DEVELOPMENT AND CONTROL
17 Single Mailbox Support EA 1.00
18 Reinstall USPS Cluster Mailbox EA 1.00
WATER SUPPY SYSTEM
19 Relocate Irrigation System LS 1.00

Download Line Items as .CSV

Pre-Bid Conference

. A Non-Mandatory pre-bid conference for this project will be held by conference call using Zoom on 2/24/2023 at 10:00 AM. 

Pre-Bid Conference Date Feb 24, 2023 10:00AM (Pacific Daylight Time) add to calendar

Vendor Questions and Answers

Submitted Questions about this Bid

These are questions submitted by vendors for which the agency has supplied an answer.

Questions
the bidders instructions say "onsite design build" does this mean that the ramps can be field fit and we will not have to submit stamped drawings to the city for approval.
Asked on 2/14/2023 4:14:33 PM
Answer:

Yes, you do not have to submit a stamped drawing. Everything is a field fit sidewalk and ramp.

 

For Questions or Additional Information, Contact:

Name: Michael Phillips
Email: bidmail@BeavertonOregon.gov

Solicitation Change History

Changes to This Listing:

Change
The bid due date has changed.
Mar 3, 2023

Share: