RFQ 4047 Chinook Gravel Trail Removal and Installation
Project #: | RFQ 4047 (ITB) |
---|---|
Issued by: | Oregon Metro |
Publish Date: | Jun 9, 2022 11:35AM |
Bids Due Date: |
Jun 30, 2022 2:00PM
(Pacific Standard Time)
|
Status: | No award issued |
Award Notes: | This solicitation has been cancelled. |
Description
Removal of existing trail:
· Removal of existing damaged asphalt trail section.
· Removal will consist of removal and disposal of duff and top organic layers down to mineral soil and backfill should be applied in 6 inch lifts and compacted until no visual displacement.
· Complete any root trimming necessary in the area and install root barrier to reduce future root encroachment.
Installation of new trail section will be consistent with option 1 in attached drawings that include:
· Raised timber side rails that are secured with re-bar that are ½’’ thickness x 18’’ minimum depth.
· Timbers for this should be 6’’x6’’ pressure treated lumber or an approved alternative with a 6 foot tread width.
· Base layer material should be a minimum of a 4’’ layer of ¾’’ minus gravel topped with a 2’’ compacted ¼’’ minus gravel with fines .
· Outslope should be 2% minimum 3% maximum.
Attachments
This project has the following solicitation documents.
You will need to:
Be logged into Bid Locker
Be registered with Oregon Metro
Express interest using the "Express Interest" button above
Vendor Questions and Answers
For Questions or Additional Information, Contact:
Please contact bidsandproposals@oregonmetro.gov with questions. Questions are due by June 23, 2022, at 2:00 p.m.
Planholders
Planholders
These are the vendors who have downloaded the solicitation documents:
Business | Contact Phone | When |
---|---|---|
Anderson Environmental Contracting, LLC (SDVOSB) | 3605779194 | Jun 14, 2022 |
ASA Construction LLC | 5039133383 | Jun 9, 2022 |
BEC Treestone Construction llc. | 5038754310 | Jun 16, 2022 |
ConstructConnect | (323) 602-5079 | Jun 13, 2022 |
Construction Bid Source | 888-786-9450 | Jun 14, 2022 |
Eugene Builders Exchange | 541-484-5331 | Jun 14, 2022 |
Plan Center Northwest | 503-650-0148 | Jun 10, 2022 |
Salem Contractors Exchange | 503-362-7957 | Jun 9, 2022 |
Seattle Daily Journal of Commerce | 2066228272 | Jun 9, 2022 |
Spokane Regional Plan Center | 509-328-9600 | Jun 15, 2022 |
Tapani, Inc. | 360-687-1148 | Jun 15, 2022 |
Tri-City Construction Council | 509-582-7424 | Jun 9, 2022 |
Twin Oaks Trails LLC | 503-757-3762 | Jun 27, 2022 |
Commodity Codes and Solicitation Change History
Commodity Codes (NIGP):
- 912-26
- Construction, Hike And Bike Trail
- 912-52
- Maintenance And Repair, Hike And Bike Trails
- 951-07
- Facilities And Other Improvements, Drives, Parking Lots, Paths, Trails
Changes to This Listing:
Change | |
---|---|
The following bid documents were added: RFQ 4047 Addendum One 06222022.pdf |
Jun 22, 2022 |