Boardman Sewer Rehabilitation Project
Project #: | 2025-WW01 |
---|---|
Issued by: | Oak Lodge Water Services |
Publish Date: | Mar 5, 2025 4:30PM |
Bids Due Date: |
Mar 27, 2025 2:00PM
(Pacific Daylight Time)
|
Price Range: | $345,000 - $380,000 |
Status: | Award pending |
Description
The Boardman Sewer Rehabilitation Project generally consists of realigning +/- 400 feet of sanitary mainline pipe near Boardman Avenue in Oak Grove, Oregon.
Line Items
This solicitation has the following line items for which you can submit a bid. Please review the bidding instructions in the bid documents for information on these line items:
Item No | Item | Unit of Measure | Quantity | Cost | Required? |
---|---|---|---|---|---|
1 | Mobilization | LS | 1.00 |
![]() |
![]() |
2 | Temporary Work Zone Traffic Control, Complete | LS | 1.00 |
![]() |
![]() |
3 | Erosion Control | LS | 1.00 |
![]() |
![]() |
4 | Bypass Pumping | LS | 1.00 |
![]() |
![]() |
5 | Construction Staking | LS | 1.00 |
![]() |
![]() |
6 | Removal of Curbs | FOOT | 44.00 |
![]() |
![]() |
7 | Removal of Surfacings | SQYD | 195.00 |
![]() |
![]() |
8 | Removal of Manholes | EACH | 1.00 |
![]() |
![]() |
9 | Tree Removal | EACH | 1.00 |
![]() |
![]() |
10 | Asphalt Pavement Sawcutting | FOOT | 627.00 |
![]() |
![]() |
11 | Mainline Video Inspection | FOOT | 401.00 |
![]() |
![]() |
12 | 10-Inch PVC D3034 Sanitary Sewer | FOOT | 401.00 |
![]() |
![]() |
13 | 18-Inch Steel Auger-Bored Casing | LS | 1.00 |
![]() |
![]() |
14 | 48-Inch Standard Manhole | EACH | 1.00 |
![]() |
![]() |
15 | Connection to Existing Manhole | EACH | 2.00 |
![]() |
![]() |
16 | Capping Existing Pipe | EACH | 2.00 |
![]() |
![]() |
17 | Manhole 6022 Base Rechanneling | LS | 1.00 |
![]() |
![]() |
18 | Concrete Curb | FOOT | 44.00 |
![]() |
![]() |
19 | Trench Resurfacing | SQYD | 202.00 |
![]() |
![]() |
20 | Remove and Rebuild Chain Link Fence | FOOT | 69.00 |
![]() |
![]() |
Attachments
This project has the following solicitation documents.
You will need to:
Be logged into Bid Locker
Be registered with Oak Lodge Water Services
Vendor Questions and Answers
Submitted Questions About This Bid
These are vendor questions for which the agency has supplied an answer.
Questions | |
---|---|
In regard to the bore on the boardman 18" bore. I noticed substantial completion is May 30th. Can this be extended to complete the bore in the dryer months (June/July)? |
Asked Mar 19, 2025 10:19AM
|
Answer:
No, the substantial completion date will remain as shown in the bid. Weather conditions will need to be a consideration for each bid line item. |
For Questions or Additional Information, Contact:
Name: Technical Services
Email: procurement@olws.org
Planholders
Planholders
These are the vendors who have downloaded the solicitation documents:
Business | When |
---|---|
AKS Engineering & Forestry, LLC |
Mar 6, 2025
(sub)
|
AKS Engineering and Forestry |
Mar 12, 2025
(other)
|
Black Rock Underground, LLC |
Mar 26, 2025
(prime, sub)
|
ConstructConnect | Mar 11, 2025 |
DJC Oregon Project Center | Mar 7, 2025 |
Emery & Sons Construction Group, LLC | Mar 6, 2025 |
Eugene Builders Exchange | Mar 7, 2025 |
James W. Fowler Co. |
Mar 7, 2025
(prime)
|
Lovett Services | Mar 13, 2025 |
N8 Holmlund Inc | Mar 11, 2025 |
Pacific Excavation | Mar 6, 2025 |
Pihl, Inc. |
Mar 7, 2025
(prime)
|
Plan Center Northwest |
Mar 6, 2025
(plan center)
|
Premier Property Development, LLC |
Mar 18, 2025
(prime)
|
Pwxpress | Mar 16, 2025 |
Salem Contractors Exchange | Mar 7, 2025 |
Seattle Daily Journal of Commerce | Mar 6, 2025 |
Settje Sons Paving |
Mar 7, 2025
(sub)
|
SLE Inc. |
Mar 20, 2025
(prime)
|
The Saunders Company | Mar 10, 2025 |
Underground Tech |
Mar 9, 2025
(sub)
|
Wallis Engineering | Mar 12, 2025 |
About Oak Lodge Water Services
Oak Lodge Water Services (OLWS) provides drinking water, wastewater, and watershed protection services to approximately 29,000 residents and businesses in Oak Grove, Jennings Lodge, and parts of Milwaukie and Gladstone.
Our system includes 208 miles of drinking water and wastewater pipes, 3,123 catch basins, and 773 fire hydrants. Additionally, we operate a wastewater treatment plant that processes over 1.5 billion gallons of wastewater each year.