Issued by: Winston-Dillard Water District
Publish Date: Oct 17, 2025 9:00AM
Bids Due Date: Dec 10, 2025 2:00PM (Pacific Daylight Time) add to calendar
Status: Open

Description

Contractor shall complete the work specified or indicated in Owner’s Contract Documents for the Project. 
The Project generally consists of the following major items of construction:

  1. Removal and disposal of existing 1 MG riveted steel tank and appurtenances including 
    piping, valves and vault at Winston Site. 
  2. Installation of temporary shoring wall to protect exisAng 0.5 M steel bolted tank at Winston 
    Site during construction. 
  3. Removal, disposal of existing 0.5 MG steel bolted tank and appurtenances at Winston Site. 
  4. Site preparation, schedule coordination and construction coordination of the new 2.0 MG 
    glass fused steel bolted tank and appurtenances as specified in the Procurement Agreement 
    between the Owner and Tank Supplier at Winston Site
  5. Furnish and install of various new valve vault, valves, manholes, piping and all other 
    appurtenances as described on the Bidding Documents and necessary for a completely 
    operation of the new Winston Tank.
  6. Furnish and installation of new Electrical and Supervisory Control and Data Acquisition 
    (SCADA) system equipment at Winston and Dillard Sites as shown in the Bidding Documents. 
    System Integration will be conducted by Owner’s Integrator, Control Systems Northwest.
  7. Furnish and install of Electrical Mixing System at Winston Site and Solar Mixing System at 
    Dillard Site.
  8. Furnish and install a new valve vault and appurtenances, a new hatch with interior ladder 
    and interior coating (floor, 3 E from floor and spot coating) at Dillard Site as described on the 
    Bidding Documents.
  9. Site grading and restoration as described on the Bidding Documents

All work is to be completed according to the schedule provided in the Contract documents. District intends 
to issue Notice to Proceed date no later than January 12th, 2026. 



For Questions or Additional Information, Contact:

Name: Tanner Pence
Email: tpence@wdwd.us

About Winston-Dillard Water District

 

Winston-Dillard Water District, located in Douglas County, Oregon, serves approximately 2,500 connections and 8,300 residents.

Our mission is to provide safe and reliable municipal services to the community we serve.

Our main water source is the South Umpqua River. Utilizing 5 water reservoirs totaling 2.75 million gallons and 128 miles of water pipeline.

Share: