Martinazzi Sewer Trunk Upsizing - Priorities 3 & 4
| Solicitation Type: | ITB |
|---|---|
| Category: | Public Improvements |
| Department: | Engineering |
| Issued by: | City of Tualatin, OR |
| Publish Date: | Apr 30, 2026 5:00PM |
| Bids Due Date: |
May 28, 2026 2:00PM
(Pacific Daylight Time)
|
| Price Range: | 4000000 |
| Status: | Award pending |
Description
City of Tualatin is accepting bids for Martinazzi Sewer Trunk Upsizing - Priorities 3 & 4, until 2:00 pm (local time), May 28, 2026, via the City’s bid management portal at https://bidlocker.us/a/tualatinoregon (“Bid Portal”), where Contract Documents may be reviewed. Specifications may also be reviewed at City Offices, located at 18880 SW Martinazzi Ave., Tualatin, OR 97062.
Bids must be submitted electronically through the Bid Portal; bids submitted by any other means will not be accepted. Richard Contreras, Procurement & Contracts Administrator, is the designated contact for this solicitation and can be reached at rcontreras@tualatin.gov or (503) 691-3080.
The City will host a virtual public bid opening at 2:10 pm (local time), May 28, 2026. Please see the Bid Portal for access instructions. A list of bidders and preliminary bid totals will be posted to the Bid Portal promptly after the virtual bid opening.
First-Tier Subcontractor Disclosure must be submitted via the Bid Portal no later than 4:00 pm (local time), May 28, 2026, two working hours after the Bid Closing.
IDENTIFICATION OF PROJECT: Major items of work include upsizing and replacement of an existing sewer trunk line, trench excavation and shoring, utility adjustments, pavement and surface restoration, traffic control, and related work.
PREQUALIFICATION REQUIREMENT: To submit a bid as a prime contractor, bidders must be prequalified by the Oregon Department of Transportation (ODOT) in the Earthwork and Drainage (EART) category no later than May 11, 2026. Additionally, any firm performing work involving Positively Restrained Shoring Systems (PRSS) must be approved by the City by submitting a Statement of Qualifications no later than 2:00 pm on May 11, 2026. Refer to Section 00120.00 of the Contract Documents for complete requirements and deadlines.
This is a contract for a public work, subject to ORS 279C.800 to 279C.870 and prevailing wage is required. Contractor must comply fully with the provisions of ORS 279C.800 through 279C.870. Contractor and subcontractors shall pay the Oregon Bureau of Labor and Industries (BOLI) wages to workers. Wage rates may be found at the following website:
https://www.oregon.gov/boli/employers/Pages/prevailing-wage-rates.aspx
Published in the Daily Journal of Commerce on May 1, 2026.
Special Instructions
PREQUALIFICATION REQUIREMENT: To submit a bid as a prime contractor, bidders must be prequalified by the Oregon Department of Transportation (ODOT) in the Earthwork and Drainage (EART) category no later than May 11, 2026. Additionally, any firm performing work involving Positively Restrained Shoring Systems (PRSS) must be approved by the City by submitting a Statement of Qualifications no later than 2:00 pm on May 11, 2026. Refer to Section 00120.00 of the Contract Documents for complete requirements and deadlines.
The City will host a virtual public bid opening at 2:10 pm (local time), May 28, 2026, the login information is below.
Line Items
This solicitation has the following line items for which you can submit a bid. Please review the bidding instructions in the bid documents for information on these line items:
| Item No | Item | Unit of Measure | Quantity | Cost | Required? |
|---|---|---|---|---|---|
| TEMPORARY FEATURES AND APPURTENANCES | |||||
| 1 | MOBILIZATION | LS | 1.00 |
|
|
| 2 | TEMPORARY WORK ZONE TRAFFIC CONTROL, COMPLETE | LS | 1.00 |
|
|
| 3 | EROSION CONTROL | LS | 1.00 |
|
|
| 4 | BAR REMOVAL | SF | 185.00 |
|
|
| 5 | POLLUTION CONTROL PLAN | LS | 1.00 |
|
|
| ROADWORK | |||||
| 6 | CONSTRUCTION SURVEY WORK | LS | 1.00 |
|
|
| 7 | REMOVAL OF STRUCTURES AND OBSTRUCTIONS | LS | 1.00 |
|
|
| DRAINAGE AND SEWERS | |||||
| 8 | TRENCH FOUNDATION STABILIZATION | CY | 50.00 |
|
|
| 9 | BOULDER EXCAVATION | CY | 5.00 |
|
|
| 10 | ROCK EXCAVATION | CY | 5.00 |
|
|
| 11 | PRSS (GREATER THAN 12 FEET IN DEPTH) | LF | 2872.00 |
|
|
| 12 | PRSS (12 FEET OR LESS IN DEPTH) | LF | 518.00 |
|
|
| 13 | VIBRATION MONITORING | LS | 1.00 |
|
|
| 14 | MAINLINE VIDEO INSPECTION, POST-CONSTRUCTION | LF | 3370.00 |
|
|
| 15 | SERVICE LINE LATERAL VIDEO INSPECTION, POST-CONSTRUCTION | EA | 42.00 |
|
|
| 16 | 12-INCH STORM DRAIN PIPE | LF | 82.00 |
|
|
| 17 | 18-INCH STORM DRAIN PIPE | LF | 5.00 |
|
|
| 18 | 24-INCH STORM DRAIN PIPE | LF | 8.00 |
|
|
| 19 | 15-INCH PVC D3034, SDR 35, 10 TO 15-FEET DEEP | LF | 137.00 |
|
|
| 20 | 15-INCH PVC D3034, SDR 26, 10 TO 15-FEET DEEP | LF | 271.00 |
|
|
| 21 | 15-INCH PVC D3034, SDR 26, 15 TO 20-FEET DEEP | LF | 681.00 |
|
|
| 22 | 18-INCH PVC D3034, PS46, 10 TO 15-FEET DEEP | LF | 915.00 |
|
|
| 23 | 18-INCH PVC D3034, PS115, 10 TO 15-FEET DEEP | LF | 475.00 |
|
|
| 24 | 18-INCH PVC D3034, PS115, 15 TO 20-FEET DEEP | LF | 532.00 |
|
|
| 25 | 18-INCH PVC D3034, PS115, 20 TO 30-FEET DEEP | LF | 359.00 |
|
|
| 26 | SERVICE LATERAL CONNECTION | EA | 42.00 |
|
|
| 27 | CONCRETE MANHOLES, 48-INCH, 10 TO 15-FEET DEEP | EA | 9.00 |
|
|
| 28 | CONCRETE MANHOLES, 48-INCH, 15 TO 20-FEET DEEP | EA | 7.00 |
|
|
| 29 | CONCRETE MANHOLES, 48-INCH, 20 TO 25-FEET DEEP | EA | 1.00 |
|
|
| 30A | CONCRETE MANHOLE, 60-INCH, 10 TO 15-FEET DEEP | EA | 1.00 |
|
|
| 30B | CONCRETE MANHOLE, 60-INCH, 20 TO 25-FEET DEEP | EA | 1.00 |
|
|
| 31 | INSIDE DROP MANHOLE CONNECTION, SEWER | EA | 13.00 |
|
|
| 32 | EXTRA FOR MANHOLES OVER EXISTING SEWERS | EA | 1.00 |
|
|
| 33 | CONNECTION TO EXISTING STRUCTURES | EA | 3.00 |
|
|
| 34 | FILLING OF ABANDONED STRUCTURES | EA | 1.00 |
|
|
| 35 | SANITARY SEWER BYPASS PUMPING | LS | 1.00 |
|
|
| 36 | TRENCH RESURFACING, TEMPORARY ACP, 3 INCH DEPTH | SY | 2300.00 |
|
|
| 37 | TRENCH RESURFACING, PERMANENT ACP, 6 INCH DEPTH | SY | 3000.00 |
|
|
| WEARING SURFACES | |||||
| 38 | SLURRY SEAL | SY | 13900.00 |
|
|
| 39 | CONCRETE CURBS, CURB & GUTTER | LF | 50.00 |
|
|
| 40 | CONCRETE DRIVEWAYS | SF | 20.00 |
|
|
| 41 | CONCRETE WALKS | SF | 400.00 |
|
|
| 42 | EXTRA FOR NEW RAMPS | EA | 1.00 |
|
|
| 43 | TRUNCATED DOMES ON NEW SURFACES, CURB RAMP | SF | 10.00 |
|
|
| PERMANENT TRAFFIC CONTROL AND GUIDANCE DEVICES | |||||
| 44 | PAVEMENT BAR, TYPE AB | SF | 240.00 |
|
|
| WATER SUPPLY SYSTEMS | |||||
| 45 | 6-INCH DUCTILE IRON PIPE WITH CLASS B BACKFILL | LF | 19.00 |
|
|
| 46 | 8-INCH DUCTILE IRON PIPE WITH CLASS B BACKFILL | LF | 8.00 |
|
|
| 47 | 10-INCH DUCTILE IRON PIPE WITH CLASS B BACKFILL | LF | 5.00 |
|
|
| 48 | DUCTILE IRON PIPE COUPLING, 6-INCH | EA | 6.00 |
|
|
| 49 | DUCTILE IRON PIPE COUPLING, 8-INCH | EA | 2.00 |
|
|
| 50 | DUCTILE IRON PIPE COUPLING, 10-INCH | EA | 2.00 |
|
|
| 51 | 6-INCH HYDRA-STOP INSTA-VALVE 250 | EA | 2.00 |
|
|
| 52 | 8-INCH HYDRA-STOP INSTA-VALVE 250 | EA | 1.00 |
|
|
| 53 | 10-INCH HYDRA-STOP INSTA-VALVE 250 | EA | 1.00 |
|
|
| 54 | 1-INCH TYPE "K" SOFT COPPER TUBE WATER SERVICE LINE | LF | 400.00 |
|
|
| 55 | RECONNECTING EXISTING WATER SERVICE LINES, 1-INCH | EA | 14.00 |
|
|
Attachments
This project has the following solicitation documents.
Vendor Questions and Answers
Submitted Questions About This Bid
These are vendor questions City of Tualatin, OR has answered. There may be other questions with an answer pending, in case you have submitted a question but don't see it here.
| Questions |
|---|
|
Question:
Reference: Section 00405.41(f)/ (2) Design Criteria, Bullet No. 5 Can trench shields / trench boxes be installed using the “Dig & Push” method for excavations less than 20 feet deep, provided that supporting engineering documentation is submitted demonstrating compliance with the applicable PRSS requirements? Please confirm whether this installation method is acceptable under the project specifications and identify any additional submittal or approval requirements that may apply. |
|
Answer:
This question was submitted after the request for clarification deadline.
The City will address trench system submittals and proposed installation means and methods with the awarded contractor during contract administration. The City reserves the right to require compliance with the contract documents and original specified requirements. |
For Questions or Additional Information, Contact:
Name: City of Tualatin Procurement
Email: rcontreras@tualatin.gov
Interested Parties and Planholders
Interested Parties
These are the vendors who have expressed interest in this solicitation:
| Business | When |
|---|---|
| BLACKLINE INC | May 18, 2026 |
| Braun Construction & Design, LLC | May 1, 2026 |
| Core And Main | May 4, 2026 |
| DJC Oregon Project Center | May 1, 2026 |
| Dodge Construction Network | May 2, 2026 |
| Emery & Sons Construction Group, LLC | May 1, 2026 |
| Eugene Builders Exchange | May 1, 2026 |
| James W. Fowler Co. | May 15, 2026 |
| K&E Excavating, Inc. | May 1, 2026 |
| Kerr Contractors Oregon, LLC | May 4, 2026 |
| Molecular - Epoxy Coatings | May 18, 2026 |
| Plan Center Northwest | May 1, 2026 |
| Salem Contractors Exchange | May 1, 2026 |
| Seattle Daily Journal of Commerce | May 1, 2026 |
| Tri-City Construction Council | May 1, 2026 |
Planholders
These are the vendors who have downloaded the solicitation documents:
| Business | When |
|---|---|
| BLACKLINE INC | May 18, 2026 |
| Braun Construction & Design, LLC | May 1, 2026 |
| ConstructConnect | May 26, 2026 |
| DJC Oregon Project Center | May 1, 2026 |
| Dodge Construction Network | May 2, 2026 |
| Emery & Sons Construction Group, LLC | May 1, 2026 |
| Eugene Builders Exchange | May 1, 2026 |
| Hilea Excavating LLC. | May 21, 2026 |
| James W. Fowler Co. | May 15, 2026 |
| K&E Excavating, Inc. | May 1, 2026 |
| Kerr Contractors Oregon, LLC | May 4, 2026 |
| Landis & Landis Construction, LLC | May 26, 2026 |
| Moore Excavation Inc. | May 19, 2026 |
| Plan Center Northwest | May 1, 2026 |
| Pwxpress | May 1, 2026 |
| ROGER LANGELIERS CONSTRUCTION | May 7, 2026 |
| Salem Contractors Exchange | May 1, 2026 |
| Seattle Daily Journal of Commerce | May 1, 2026 |
| Tri-City Construction Council | May 1, 2026 |
| Westlake Consultants, Inc. | May 14, 2026 |
Solicitation Change History
Changes to This Listing:
| Change | Date | Is Addendum? |
|---|---|---|
| The following bid documents were added: Addendum #1 - Martinazzi Sewer Trunk Upsizing Priorities 3 & 4.pdf |
May 14, 2026 |
|
| The following bid documents were added: Addendum #2 - Martinazzi Sewer Trunk Upsizing Priorities 3 & 4.pdf |
May 20, 2026 |
|
About City of Tualatin, OR
With nearly 28,000 residents, the City of Tualatin is a dynamic, vibrant community conveniently located just 12 miles south of Portland and 30 miles north of Salem, the state capital. Situated at the intersection of Interstate highways 5 and 205, Tualatin is a short distance to adventure, from the Cascade Mountain Range to the Oregon Coast.